2018 a year in review
January
began very mild with very little snow. Pikes Peak showed bare most of the
month. Upper canal work began replacing cement lining that over time, slipped,
cracked or broken beyond repair. The project is funded with Grant monies we
received from CWCB. The main purpose is to increase water retention to Brush
Hollow.
February
work continued on the upper ditch relining project. The annual shareholders
meeting was a great success with 66% of the shareholders represented either in
person or though proxy. Jack Tyler was re-elected to the Board for another 3 years.
The shareholders voted to pay off BPW debts with CWCB using part of the 2.6
million currently in CD’s with Edward Jones. Additionally they voted favorably
to move forward on the new proposed contract with Penrose Water District for
years of 2021-2025. The shareholders also approved to continue the $13.00
surcharge as part of the assessments for capital improvements. Total annual
assessments with continue to be $78.00 per share.
Ballot item #2 proposed changes to the Articles of Incorporation
and By-laws were accepted with a vote of 2196 voting yes to 29 voting no. It
was discussed that our area is currently under drought conditions with little
snow and unless something changes, irrigations would be limited this year.
March
did provide us with some snow and rain; however the wind helped dry up what
little moisture we did receive. The upper ditch relining was completed and the
staff worked many hours cleaning canals and fixing lines and boxes needing
repair. Brush Hollow’s level at 90ft gave us promise to begin irrigations in
April. Due to an injury, we looked for a temporary ditch rider to fill in when
irrigation begins.
April
the staff completed cleaning and began running irrigations on the 16th.
Unfortunately the wind played a mean trick and filled the canals with dirt and
debris clogging up the entire system. After hours of cleaning screens
constantly it was decided to shut the water off due to flooding the clogs were
causing. It took several days to clean and haul off debris however irrigation
did start up again on the 23rd. Penrose did actually receive some
snow and rain, enough to visually see fields green up.
May was
the beginning of what the drought had brought to our area. Typically we are
experiencing snow melt down the creek; however the creek was running low.
Running irrigation with less water meant less lines running and this extended
normal irrigation times significantly. The only saving grace was that Brush
Hollow was full when we started.
June
the struggle continued with very little water coming down the creek. It was
determined that each shareholder would only receive one irrigation as we had to
keep Brush Hollow no lower than 70 feet to meet our obligations with Penrose
Water district and the fish habitat. Providing irrigators on the upper ditch
was a challenge with very little water coming down. Not only are we in a
drought; it was so dry our area was put under stage 2 fire restrictions.
July
brought us extreme heat with clear and dry skies. Temperatures were in the high
90’s. We had to discontinue irrigations as the creek ran dry for almost 3
weeks. No water was reaching our diversion. The middle of the month water
finally began to flow again. This enabled us to fill the diversion and finish
irrigations. Our temporary ditch rider became a regular ditch rider as Larry
Feyerherm’s last day was the end of June.
August
finally provided the area with some well needed precipitation. Temperatures
were still in the upper 80’s and 90’s. The creek was running enough water down
it to provide Penrose Water District and pass down to Brush Hollow. We still do
not have enough water to begin second irrigations. Ditch Rider Charlie Avila
resigned to begin a job in Colorado Springs. We will not fill the position
until the beginning of next year as irrigations are not running.
September
was very warm and very little precipitation was received. Brush Hollow has only
risen 3 feet in the past 2 months with the small amount of water we have
received down the creek. Steve Kastner, our engineer was successful in applying
for additional Grant monies to continue our relining the upper ditch. This
provided us with an additional $80,000 of Grant money for phase 2.
October
our area finally received some snow and rain that equaled almost an inch of precipitation.
Temperatures did drop enough to freeze the apple crops that shortened the
growing season. We continue to receive enough water to pass to Brush Hollow which
will help us in the spring.
November
provided us winter temperatures with little moisture. The staff continued to
work on repair projects. They replaced a line on the West side that has been a
problem for at least 2 years.
December
has continued with winter day time temperatures in the 40’s-high 50’s and
nights as low as 7 degrees. However we have received no precipitation. We
probably will not have a white Christmas here in Penrose. The weather patterns
show possibly some chance of snow after Christmas. The upper ditch relining
project is up and running again with the temperatures delaying the delivery of
cement. We are hopeful to finish as soon as possible as we were unable to
capture the water as we did last year. We are actively seeking a ditch rider
position to be filled. Resumes are being accepted in the office. Interviews
will begin after the first of the New Year. The Board of Directors and the
staff wishes everyone a safe holiday season. Merry
Christmas and Happy New Year.