10.30.2020

October 2020 Update

 October’s weather for Penrose went from Summer temperatures 86 degrees on the 5th to Winter on the 27th with a high of 17 degrees. We did experience a very wet snow accumulating between 8-12 inches depending on where you live but unfortunately the total precipitation was only ¼ of inch.

The upper ditch lining is in full swing and the Winter weather set back the anticipated completion date of October 31st, as cement could not be delivered for several days. On the West side our “Grand Canyon” project on the upper ditch is very close to completion. All the pipe is in place. We are waiting for the transitions from both sides to be completed and clean-up of the area. This also is a cement project that has been delayed due to the weather conditions. We are hopeful that the weather will be kind, and not delay these projects much longer.

We have one more project this fall to be completed and that is the gate replacement at our diversion. This is the gate that opens up into Beaver Creek and has had a continued leakage issue over the past several years. It was determined that replacement of the gate was our only option as an onsite evaluation discovered over time it has deteriorated beyond repair. Water loss overtime has been significant and with drought conditions we can’t afford to lose any water.

When our area was not classified under a red-flag warning, mowing continued. In order to keep the canal dry for the upper ditch lining, a temporary dam was placed in at L St. this water was used by Shareholders rather than spilling over down the creek to the Arkansas.

Please remember to be thankful for what you do have as we enter the Thanksgiving Season.